The three photos below show the attenuation tank being installed. This tank collects the water from the roof and car park and controls the rate at which water enters the main drain. The tank is under the entrance to the car park, between the four ground source heat pipes. All the rest of the drains for the hall are now in place.
The roof felting is now complete on the main hall ready for the tilers, whilst the store area at the front of the build, facing the car park is in the first stage of roofing.
Although the work schedule is two weeks behind, to make up for lost time Wildgoose are generally going to be working on a Saturday.
Thank you to Robert & Ben for the photos.