The weather continues to be our enemy, with stoning and block work only happening when the temperature is suitable. However, lots of jobs are still continuing. All the block work is almost to roof level, this means that the woodwork for the roof over the foyer and toilets is being put in place. All the internal walls are in situ, so it is now recognisable as a main hall with meeting room, toilets, kitchen and foyer. The first photo shows the end wall of the kitchen block, nearest the Legion and has been built by Phil and his brother John from Longnor. The other photo is looking down on the kitchen and shows the meeting room; the gap where it is angled will be glass doors opening onto the patio.

Thank you to Robert (Site Manager) for these photos.