This week has been a busy week, with Wildgoose working today to help make up for some of the days lost during the recent snow. The joiners have been preparing the roof for felting, hopefully this will happen next week. Internal block work has been rapidly continuing, and all the internal walls can now be seen. The ground heat source pump has been pressure tested ready for future connection.

This photo is taken from the back on The Legion and the block work on the left will be the kitchen. The area between the kitchen and the main hall will be the meeting room. The ground in front will be the patio area with raised planted beds and will be a secure play area for Stepping Stones and the Toddler Group.

This wall is the rear of the kitchen and runs alongside the footpath leading towards The Square.
Thanks to JF-S for the photos.