Again the builders have been working 7 days a week, with 6 guys in today. This week has seen the completion of the main roof, which is fully tiled and has two solar panels on the rear. The small structure in the middle of the roofline, when finished will be the ventilation system for the hall, and will be placed in situ by crane.


The carpenters have finished the floor for the high level storage above the hall, this area is designated for items such as scenery flats, costumes etc for future stage productions (calling all thespians, get your thinking caps on).
The plasters have been prepping the hall ready for plastering this week. Plumbing, electrical work and further insulation continues, as does the external pointing on the stonework.

Thanks to Ben & JF-S for the photos.