Work on repairing the B5056 at the landslip just north of the Bentley Fenny Bentley is to start on Monday 11th January. Here is the County Council’s update:
I can confirm that the start date for the Fenny Bentley landslip works is 11 January 2010. Along with nearly all civil engineering contractors and suppliers the Contractor for the works shuts down for a fortnight at Christmas, returning to work on 4 January. During his first week back he will be busy mobilising the plant, equipment and materials required on site. He will also have to arrange his site accommodation, mess and welfare facilities.
Regards,
Brian Martin
Senior Project Engineer